Ongoing Fibre Projects

ProjectStatusEst. Completion
Egmondville into SeaforthHook ups starting shortly.Spring 2022
Clinton to Londesboro [London Road]Hook ups to begin shortly, construction completeSummer 2022
BornholmConstruction nearly completed, hooks ups to begin this winterSummer 2022
Morris RoadConstruction nearly completedSummer 2022
Roxboro LineConstruction begunSummer 2022

Upcoming Fibre Projects

ProjectStart Date
HenfrynWinter 2021
Central Huron WestSpring/Summer 2022
Central Huron EastSpring/Summer 2022